1. Portfolio Prioritisation beginner

    A quarterly plan allocates 100% of engineering capacity to roadmap features. The rationale is that maintenance work can be picked up as it arises. Review the plan.

    2 min answer capacity planningmaintenancedependency currencyprioritisation
  2. Portfolio Prioritisation intermediate

    An architecture team has more improvement proposals than capacity. How should they be prioritised?

    2 min answer prioritisationriskleveragesequencing
  3. Portfolio Prioritisation intermediate

    An organisation has forty proposed initiatives and capacity for eight. What framework produces a defensible portfolio, and what does it need to avoid?

    2 min answer myntraprioritisationportfoliosequencing
  4. Portfolio Prioritisation intermediate Multiple choice

    Three funded initiatives each need about six weeks of work from the same two-person identity team, which also absorbs roughly 30% of its time in unplanned support. All three sponsors want to start now and the plan shows all three starting now. Which rule should decide the sequence?

    3 min answer prioritisationconstraintscost of delaywip
  5. Portfolio Prioritisation advanced

    You are the architect in an annual portfolio review. Eight initiatives are funded for the year out of forty proposed; none of them is yours. Five of the eight need changes to the same entitlement component, which is owned by a three-person team that also absorbs unplanned support. What do you bring to that meeting that the product directors cannot, and how do you get enabling work funded when it has no business case of its own?

    3 min answer portfoliodependenciesfundingsequencing