1. Decommissioning advanced Multiple choice

    A replaced system was made read-only for 30 days. No complaints came in and it was switched off, with its data exported to an archive. Three weeks later the annual regulatory extract fails, because the job read directly from the retired database. Which design decision made this possible?

    3 min answer decommissioningbatchregulatoryobservability
  2. Legacy Assessment intermediate

    A team inherits a system nobody fully understands and is asked whether to rewrite it. What should be established before answering?

    2 min answer freshworksassessmentrewriteunderstanding
  3. Legacy Assessment advanced

    A twenty-year-old core system supports most of the business. It is on unsupported technology, three people understand it, and the last replacement attempt was abandoned after two years. Design the programme.

    3 min answer legacystranglerriskbusiness-case
  4. Legacy Assessment intermediate

    Before modernising, a team must assess a legacy system. What should the assessment measure, and what is usually skipped?

    2 min answer legacy-assessmentevidencedependenciesusage
  5. Legacy Assessment intermediate

    On Salesforce's Force.com platform, a customer's custom objects and fields are rows of metadata in shared tables rather than a schema of their own (Weissman and Bobrowski described the design at SIGMOD in 2009). What does that remove from the legacy problem, and what does it not remove?

    3 min answer salesforcemulti-tenancymetadataupgrades
  6. Legacy Integration Patterns intermediate

    A fourteen-year-old policy system sustains roughly 350 transactions per second at its measured peak and the business peak already consumes about 260 of them. Four new services want to call it directly. Roughly how much of that system can you sell them, and what does the number decide?

    3 min answer legacy integrationcapacityquotasretries
  7. Legacy Integration Patterns beginner

    A new notifications service needs customer contact data that only a twelve-year-old billing system holds. The team points it at a read replica of the billing database and ships in a week. Why does this work, and why is it still the most expensive integration they could have chosen?

    3 min answer integrationshared-databasecouplingschema-change
  8. Legacy Integration Patterns advanced

    A new platform must integrate with legacy systems that only support batch file exchange. How should the boundary be designed so the new system is not constrained by it?

    2 min answer elasticrunlegacybatchanti-corruption
  9. Legacy Integration Patterns intermediate

    New services must interact with a legacy system that cannot handle their load or their pace of change. Which integration patterns apply?

    2 min answer legacy-integrationanti-corruption-layercdcbuffering
  10. Legacy Modernization advanced

    A 15-year-old monolith runs the core of the business. Leadership wants microservices. How do you approach it, and what would make you refuse?

    2 min answer stranglermodernizationmicroservicesrisk
  11. Legacy Modernization advanced

    Most large modernisation programmes are late, over budget, or abandoned. What are the recurring structural causes, rather than the project-management ones?

    2 min answer modernisationsecond-systemcoexistencescope
  12. Legacy Modernization advanced

    TSB's 2018 core banking migration moved 1.9 million customers in a single weekend and failed publicly. What would you have required before approving that cutover?

    3 min answer migrationcutovertestingcase-study