1. Cutover Planning intermediate

    A cutover is planned for a Sunday night. What must be prepared beyond the technical steps, and what is the most commonly missing item?

    2 min answer ackocutoverrollbackrunbook
  2. Cutover Planning intermediate

    A platform must cut over a critical service. What does a cutover plan need beyond the switching steps?

    2 min answer cutoverrollbackrehearsalcommunication
  3. Cutover Planning intermediate

    What is in a cutover plan besides the steps, and what would you rehearse?

    1 min answer cutoverrollbackabort-criteriarehearsal
  4. Decommissioning intermediate

    A migration is complete and the old system is still running a year later. Why does decommissioning fail, and what makes it happen?

    2 min answer nykaadecommissioningcostrisk
  5. Decommissioning intermediate

    A replaced system is still running two years after its replacement went live. Why does decommissioning fail, and what makes it happen?

    2 min answer decommissioningunknown-consumersevidenceownership
  6. Legacy Assessment intermediate

    A replacement for a 16-year-old claims system passed every acceptance test and went live. Six weeks later the reinsurance return it produced was rejected by finance, and nothing in the test pack was wrong. An interviewer asks how you would have found that gap during the assessment. What do you say?

    3 min answer legacy-assessmentcompensating-controlsshadow-processrequirements
  7. Legacy Assessment intermediate

    A team inherits a system nobody fully understands and is asked whether to rewrite it. What should be established before answering?

    2 min answer freshworksassessmentrewriteunderstanding
  8. Legacy Assessment intermediate

    Before modernising, a team must assess a legacy system. What should the assessment measure, and what is usually skipped?

    2 min answer legacy-assessmentevidencedependenciesusage
  9. Legacy Assessment intermediate

    On Salesforce's Force.com platform, a customer's custom objects and fields are rows of metadata in shared tables rather than a schema of their own (Weissman and Bobrowski described the design at SIGMOD in 2009). What does that remove from the legacy problem, and what does it not remove?

    3 min answer salesforcemulti-tenancymetadataupgrades
  10. Legacy Integration Patterns intermediate

    A fourteen-year-old policy system sustains roughly 350 transactions per second at its measured peak and the business peak already consumes about 260 of them. Four new services want to call it directly. Roughly how much of that system can you sell them, and what does the number decide?

    3 min answer legacy integrationcapacityquotasretries
  11. Legacy Integration Patterns intermediate

    New services must interact with a legacy system that cannot handle their load or their pace of change. Which integration patterns apply?

    2 min answer legacy-integrationanti-corruption-layercdcbuffering
  12. Migration Risk intermediate

    Review this migration plan. Cutover is staged by customer cohort at 2 percent then 10 then 50 then 100. Readiness for each step is "all automated tests green and no open P1 defects". The rehearsal ran against a 5 percent copy of production. The rollback step reads "restore from the pre-cutover snapshot if data integrity is compromised". What would you remove, what would you change, and what would you leave alone?

    3 min answer migration-riskcutoverabort-criteriarehearsal